How Long Does It Take to Assemble a Hud-1 Log Cabin Kit?

How long it takes to assemble a Hud-1 log cabin kit, using the store's own FAQ figures by kit size, plus the prep, delivery and assembly options that change your schedule.

How long it takes to assemble a Hud-1 log cabin kit depends mainly on the size of the kit and the thickness of its wall logs: the Hud-1 EZ Buildings FAQ gives about 8 hours for the smallest kits, 3 to 4 days for medium kits and 3 to 4 weeks with a 3-person crew for the larger homes. Foundation work, roofing and finishing come on top of that, because the kit does not include them. You can find the current code on our Hud-1 EZ Buildings discount code page.

What the Store Says About Build Time

Hud-1 EZ Buildings answers this question on its own FAQ page and ties the time to the log size:

Kit group (store FAQ) Wall logs Assembly time (store FAQ)
Smaller kits, under 40 sq. ft. 28 mm About 8 hours
Medium kits, 130 to 200 sq. ft. 44 mm (1 3/4 in.) 3 to 4 days
Larger kits, over 800 sq. ft. 70 mm (2 3/4 in.) 3 to 4 weeks with a 3-person crew

Those figures cover putting the kit together. The FAQ also lists what the kit leaves out: roofing materials, electrical, plumbing, cabinets, countertops, light fixtures, bathroom fixtures, insulation and the foundation. Each of those is a separate job with its own schedule, so plan them in addition to the times above.

The FAQ does not give a time for kits that fall between its groups, such as a 300 or 600 sq. ft. building. If your model sits in that gap, ask the store for an estimate for that exact kit before you book help or rent equipment.

How the Kit Size Changes the Schedule

The product pages show which group each building belongs to:

Lama j44 log cabin chalet kit
Lama j44 log cabin chalet kit$32,526.85Image from the merchant
  • Lama J44 log cabin chalet: 1 3/4 in. x 4 1/2 in. interlocking kiln dried wall logs, 364 sq. ft. of open space and a purlin roof with 3/4 in. tongue and groove deck boards, per its product page.
  • Log Garage D2: 1 3/4 in. tongue and groove wall logs and an internal size of 16.75 ft. x 18.84 ft., per the store.
  • Grill Cabin S: a 12 ft. x 12 ft. grilling cabin with 1 3/4 in. wall logs and 151 sq. ft. inside, per its product page.
  • Garage 25J: 2 3/4 in. premium logs and 750 sq. ft. inside, per the store.
  • Felix J68 two story log cabin: 2 6/8 in. interlocking wall logs and 1054 sq. ft. of interior heating space, with 2 bedrooms and a bathroom, per its product page.
  • Cameron log home kit: a 43 ft. 9 in. x 28 ft. 4 in. ranch style multi room design with 2 3/4 in. tongue and groove wall logs, per the store.

The Felix J68 and the Cameron are in the store’s “over 800 sq. ft.” group, so the 3 to 4 week figure for a 3-person crew is the one the store gives for builds of that size. The 1 3/4 in. log buildings have thinner walls, but several of them are larger than the 130 to 200 sq. ft. medium group, so treat the 3 to 4 day figure as a floor, not a promise.

What to Do Before the Kit Arrives

Much of the time you can save is won before delivery. The store’s pages list several facts that shape your prep:

  • Lead time. The FAQ says delivery takes 10 to 12 weeks for made-to-order kits after payment clears. Use that window to get the foundation finished and ready.
  • Foundation. Product pages such as the Felix J68 say the building is ready to mount on your provided foundation and mounts to a slab, wood block or skid style foundation. A concrete slab has to cure before you build on it, so pour early.
  • Unloading. Kits ship curbside, and the Cameron page states that unloading is the buyer’s responsibility. Arrange people and equipment for delivery day.
  • Checking the parts. The A-frame and Grill Cabin warranty text asks you to open and inspect all boxes within 30 days of delivery and check them against the parts list. Doing this before you start avoids stopping halfway for a missing piece.
  • Tools. The store’s A-frame page lists a drill, saw, wood or rubber mallet, ratcheting tie down and hammer. Have them on site before day one.

DIY or Store Assembly

If you would rather not build it yourself, the store’s FAQ says assembly can be provided in select locations in Tennessee, Mississippi and Alabama, and the Grill Cabin page also lists Georgia, Missouri and Arkansas. The FAQ gives one price example: $9.00 per sq. ft. under roof for the Jackson, Tennessee area, within 25 miles of the main office. Outside that area the store says it cannot speak for local costs, so get prices from builders near you.

For a DIY build, the store’s own time figures assume a crew for the larger kits. The wall logs stack and interlock, and the larger kits have long walls and a roof with purlins and deck boards, so plan enough helpers for lifting and holding parts in place. Weather matters too: bare wood should not sit out in the rain for weeks, and the warranty on premium kits depends on proper wood treatment, with two wood seal treatments recommended on the product pages.

After the shell is up, roofing, sealing, wiring, plumbing and interior work add their own time. Your local building department may also need to inspect at set stages, which can decide when the next step can start.

Questions

How long does it take to assemble a Hud-1 log cabin kit?

The Hud-1 EZ Buildings FAQ gives about 8 hours for small kits with 28 mm logs under 40 sq. ft., 3 to 4 days for medium kits with 44 mm logs of 130 to 200 sq. ft., and 3 to 4 weeks with a 3-person crew for larger kits with 70 mm logs over 800 sq. ft.

Does the build time include the roof and foundation?

No. The store FAQ says the kit excludes roofing materials, the foundation, insulation, electrical, plumbing and fixtures. Those jobs add time on top of assembling the kit.

How long does delivery take?

The store FAQ says delivery takes 10 to 12 weeks for made-to-order kits after payment clears, and times may vary by location and floor plan.

Can Hud-1 EZ Buildings assemble the kit for me?

The store says assembly can be provided in select locations in Tennessee, Mississippi and Alabama, and one product page adds Georgia, Missouri and Arkansas. Its FAQ quotes $9.00 per sq. ft. under roof for the Jackson, Tennessee area, within 25 miles of its main office.

What tools do I need to assemble the kit?

The store lists a drill, saw, wood or rubber mallet, ratcheting tie down and hammer on its A-frame product page. Check the instructions for your own model for anything extra.